Construction Update - February 2018
Please see below for our drone construction video update.
Estate Works
Stage 1 Park – Our first park is now complete.
Bio Retention Basin (near Stage 2) – Works have commenced.
Korkuperrimul Creek Reserve – Trees planted in 2015 and 2016 are thriving. Construction of a parkland area adjacent to Stages 1, 2 and 3a will commence in September 2018.
Werribee River Reserve – 3,000 tube stocks were planted along the Werribee River adjacent to the future Rivers Edge precinct. There are plans for 10,000 more trees to be planted.
Construction Update
Stage 1 – Stage 1 was titled in December 2017.
Stage 2 – The road base and kerb and channel are complete. Construction is expected to finish in March 2018. Depending on all approvals, titles are expected in May 2018.
Stage 3 – Construction of services continues. We anticipate to complete construction in May 2018, with titles expected in July 2018.
Rivers Edge Stages 5 & 6 – Construction is expected to commence in April 2018, with titles expected in December 2018.
Rivers Edge Stages 7 & 8 – Construction will begin in the second half of 2018 with titles expected in the first half of 2019.
River View Stages 9 & 10 – We anticipate that construction begin in the first half of 2019.
River View Stage 11 – Currently Selling.