Underbank Construction Updates   

  

 

 

Stage 19

 

Regarding the feedback from the site review session with Melbourne Water on 22/02/2024 and advice from engineers, the Rock Chute can be closed out in 2 weeks, and the Stage 19 settlement can be expected in April 2024, depending on MW's response.

 

 

 

River View (S901 Townhouse)

 

Majority of the civil works are now complete, however further works are currently on hold due to a delay in Powercor approving the revised electrical plan. We anticipate approval either later this week. Approximately four more weeks of work are anticipated after Powercor's approval to reach practical completion. Settlements are expected to occur in April 2024.

We sincerely apologize if this delay has caused any inconvenience. 

 

Park View (21-23) 

 

 

Construction work for Stage 21-23 is on program. 

 

 

 

Underbank Planning Updates 

 

 

Rose Hill (Stages 1 - 3)

 

Detailed Engineering plans for Stage 3B are awaiting Council approval.  

 

Park View (Stages 24 - 29) 

 

 

Stage 24 features 23 lots with block sizes ranging from 444 m2 - 720 m2, this diverse stage ensures there's something for everyone. Here, residents can breathe fresh country air in some of Victoria's most expansive land. You can also enjoy the scenic views and admire the beautiful river red gums that line the creek, along with a range of urban amenities.

 

S901 townhouse now selling in Underbank

 

 
S901 townhouses is near Central Park and the Town Centre in River View. These stunning architecturally inspired designs come with complete park frontage and have been designed to maximise the amazing views that are on offer within this location.
 
Don't miss out on this affordable release of two-story luxury townhouses in a great location.
 
 
 

 

Visit our Underbank website for moreVisit our Underbank website for more information by clicking the link below.

Available Land for Sale

Underbank Construction Updates   

 

 

 

 

 

Stage 19

 

Regarding the feedback from the site review session with Melbourne Water on 22/02/2024 and advice from engineers, the Rock Chute can be closed out in 2 weeks, and the Stage 19 settlement can be expected in April 2024, depending on MW's response.

 

 

 

River View (S901 Townhouse)

 

Majority of the civil works are now complete, however further works are currently on hold due to a delay in Powercor approving the revised electrical plan. We anticipate approval either later this week. Approximately four more weeks of work are anticipated after Powercor's approval to reach practical completion. Settlements are expected to occur in April 2024.

We sincerely apologize if this delay has caused any inconvenience. 

 

Park View (21-23) 

 

 

Construction work for Stage 21-23 is on track. 

 

 

 

Underbank Planning Updates 

 

 

Rose Hill (Stages 1 - 3)

 

Detailed Engineering plans for Stage 3B are awaiting Council approval.  

 

Park View (Stages 24 - 29) 

 

 

Stage 24 features 23 lots with block sizes ranging from 444 m2 - 720 m2, this diverse stage ensures there's something for everyone. Here, residents can breathe fresh country air in some of Victoria's most expansive land. You can also enjoy the scenic views and admire the beautiful river red gums that line the creek, along with a range of urban amenities.

 

S901 townhouse now selling in Underbank

 

 
S901 townhouses is near Central Park and the Town Centre in River View. These stunning architecturally inspired designs come with complete park frontage and have been designed to maximise the amazing views that are on offer within this location.
 
Don't miss out on this affordable release of two-story luxury townhouses in a great location.
 
 
 

 

Visit our Underbank website for moreVisit our Underbank website for more information by clicking the link below.

Available Land for Sale

Back to News & Events