Construction Stage Overview

 

We hope you & your families had a wonderful festive season and are staying safe & well. 

I am pleased to advise that the part of Underbank that was in Pentland Hills has now been renamed Bacchus Marsh by Moorabool Shire Council. This means that all of Underbank is now located in Bacchus Marsh.

Our Underbank Sales & Information Centre has resumed normal 7-day operations so if you are looking for land please get in touch with our Estate Manager John at 0429 805 147 and book a site visit.

Blocks in Underbank are currently in high demand, please register your interest by clicking the below link for our future releases. The next release will be Townhouses near Central Park and the Town Centre in River View; don't miss out on this affordable release of two-story luxury townhouses in a great location; never to be repeated. Register your interest now.We hope you & your families had a wonderful festive season and are staying safe & well. 

Follow us on Social Media!

Facebook      Instagram

 

Underbank Construction Updates

 

River View (Stages 9 - 12)

Construction work is progressing well; although heavy rain in December and last week has slowed progress on the creek crossing and bio-treatment basins. Construction on these structures needs to be completed before we can obtain titles for Stages 9 to 12. Currently, we expect settlements for Stages 9 to 12 to occur in early to mid-April 2022. This is only about two months away so please contact your lender so that their valuers can visit the site and prepare your loan for settlement. Also, you will want to inform your builder that the settlement is not far away.


River View (Stage 13)


Stage 13 subdivision works commenced in June and are currently progressing well, and we expect settlements to occur around mid-2022.

 


River View (Stages 14 - 19)

Stage 14 to 19 subdivision works are currently progressing well, and we expect settlements to occur in the last quarter of 2022 or first quarter of 2023. Underbank Planning and Post Construction Updates


Underbank Construction Updates

 

River View (Stages 9 - 12)

Construction work is progressing well; although heavy rain in December and last week has slowed progress on the creek crossing and bio-treatment basins. Construction on these structures needs to be completed before we can obtain titles for Stages 9 to 12. Currently, we expect settlements for Stages 9 to 12 to occur in early to mid-April 2022. This is only about two months away so please contact your lender so that their valuers can visit the site and prepare your loan for settlement. Also, you will want to inform your builder that the settlement is not far away. River View (Stage 13) Stage 13 subdivision works commenced in June and are currently progressing well, and we expect settlements to occur around mid-2022.


River View (Stages 14 - 19)

Stage 14 to 19 subdivision works are currently progressing well, and we expect settlements to occur in the last quarter of 2022 or first quarter of 2023. Underbank Planning and Post Construction Updates

 

Stage 1 - 3

Detailed Engineering plans for Stage 3B are awaiting Council approval. We expect the construction of Stage 3B to commence around the middle of 2022.

 

Rivers Edge (Stages 5 - 8)

Street tree planting and other landscaping in Rivers Edge has recently been completed.

 

River View (Stages 9 - 19)

Engineering plans for Stages 9 - 19 have been approved and sent out to the prospective purchasers. If you are purchasers of Stages 9 - 19 and have not received the Approved Engineering Plan, feel free to send your enquiries to underbank@kataland.com.au

 

Park View (Stages 21 - 29)

The planning permit for Stages 21-23 has been received from Council and detailed engineering plans are currently with Council for approval.

 

A planning permit application for Stages 24 to 29 has been submitted to Council and we expect to receive the permit in the second quarter of 2022.

 

More than 95% of lots have been sold—please contact our Estate Manager John at 0429 805 147 if you would like to purchase land in these stages.