Underbank Newsletter Updates - September 2025

 

Underbank Construction Updates     

 

River View
Stage S1301 construction work is in progress.

 

Park View
We finally received approval from Melb Water in late May and commenced construction of the culvert and associated creek works on 23 June 2025. This delay in Melb Water approval means settlements for stages 21 - 23 will occur in Dec 2025, and stage 24 will be in Jan/Feb 2026. 

  

Town Centre
We are currently in the process of rezoning the town center land to commercial use. The Council has requested an indicative layout, which has been prepared by our planning consultant. Additionally, we have engaged a consultant to design the retail component and layout.

 

 

We thank you for your continued support and patience, and look forward to sharing more exciting updates with you soon.


 

 

River View (S901 Townhouse)

 

Stage S901 Townhomes – Roofing works are substantially complete, and solar panel installation is visible across several units. External façades are partially finished.

 

River View (S1301)

 

 

Stage S1301 –  Construction completion is targeted for October.

 

Park View (21-24) 

 

Stages 21-24 – Concrete culverts are partially installed with ongoing excavation and backfilling. Road connections to the estate are visible, but internal roads and landscaping remain incomplete. 

 